p ( 21 )
Item | Details of Works | Quantity and Unit | Price | Amount
Fils Dinar
29 | Reinforced concrete with a ratio of 1-2-4 for foundations
according to the maps issued or to be issued by
the specialized engineer. | 3129 - | 12.000 | 37548/000
1225 / 600
18
30 | Painting with Snowcem three coats in a very good
manner. | 250 m2 | 0.120 | 60.000
31 | Digging and building a complete cesspool with a depth not less
than 3 meters and a diameter from the bottom
of 3 m and built with good bricks and clay | Number
1 | 5.000 | 450.000
32 | Mosaic steps for the stairs (according to
the design provided by the <del>specialized engineer</del>)
Precast. | 70 ft. r | 1.500 | 105.000
33 | Entrance door made of teak wood (
according to the design provided by the <del>specialized engineer</del>)
and the frame size shall be 6" by 3". | Number
54 | 0.250 | 13.500
34 | Hooks for ceiling fans and they shall be
of excellent type. | 30 number | 0.700 | 21.000
35 | Jack arching with bricks and gypsum, provided that
the gypsum is of the new hot type and the bricks are of
the excellent type. | 500 m2 | 0.250 | 125.000
36 | I-beams and incline, and it shall be of the English
or Belgian type, new blue
color, free of rust, and in the size
required by necessity. | Ton
2 | 25.000 | 1250.000
37 | Gully size 4" independent English with installation
and cover. | 1 number | 0.725 | 0.725
38 | Partitions with bricks and cement, cement mixing
1 = 4. | 1000 m2 | 0.207 | 250.000
39 | Painting with distemper (Dry Distampar)
and it shall be of the excellent type and not mixed
with gypsum. | | |
1084/7525
Page 27
p. 33
Item | Details of Works | Quantity | Price | Amount
Fils Dinar
| | | | 20848 / 525
40 | Spiral doors for shops | 105 m2 /0 | 1.500 | 157 / 500
41 | Reinforced concrete for column bases under
ground with formwork, mix ratio 1-2-4 | 3 m3 /0 | 17.500 | 52.500
42 | <del>Reinforced concrete with formwork for tie beams</del>
⟦above line:⟧ for tie beams
to ground level at a ratio of 1-2-4 | 3.65 m3 /0 | 16.500 | 60.225
43 | Pouring polished concrete 15 cm thick, ratio
1-2-4 | 1 m2 /0 | 0.750 | 0.750
44 | Polished concrete steps for the stairs
ratio 1-2-4 | ⟦illegible⟧ | 0.900 | 0.900
45 | Encasing sewage pipes with concrete
ratio 1-2-4 | 45 m. p. /0 | 0.350 | 15.750
46 | Cement slurry under gypsum plaster
ratio 1-1 | 350 m2 /0 | 0.080 | 28.000
47 | Cement pointing of the ironed type | 220 m2 /0 | 0.120 | 26.400
48 | Brickwork with cement 1-4 | 1 m3 /0 | 4.500 | 4.500
49 | Glass brick construction for walls <del>⟦illegible⟧</del> | 50 ft2 /0 | 9.000 | 450.000
50 | Seryosh according to the maps | 35 m2 /0 | 6.000 | 210.000
51 | Cement coating for skirting (2500/0 m2) | <del>2500/0</del> 350 m2 | 0.350 | 122.500
52 | Electrical installations including boards,
main switch, fuses .. etc | Lump sum | 75.000 | 75.000
53 | Leveling the ground and demolishing the existing building
and transporting all debris after the committee
takes what it wants from that debris | Lump sum | 50.000 | 50.000
54 | Guarding, water supply, paying expenses
and providing electric current in case of
need and paying all expenses | Lump sum | 100.000 | 100.000
55 | Cleaning the building, wiping the glass and making it complete
in all aspects | Lump sum | 25.000 | 25.000
56 | Pipes for fresh water and sewage
including elbows, joints and tees
and everything the work requires
6 - Galvanized pipes with diameter <del>inch</del> ⟦above line:⟧ 1 inch for washbasin water 15 m. p. | 15 m. p. | 0.900 | 13.500
⟦line⟧
22977 / 825
Page 28
Amount
Fils Dinar | Price | Quantity | Work Details | Item
<del>2377/820</del>
29.220 | 0.650 | 50 m.p. | Galvanized pipes diameter 1 inch | B
20.250 | 0.450 | 50 m.p. | = 3/4 = = | C
10.000 | 0.200 | 50 m.p. | = 1/2 = = | D
1.000 | 0.500 | 2 Units | 1 inch lock | E
0.800 | 0.400 | 2 Units | = 3/4 = | F
0.700 | 0.350 | 2 Units | = 1/2 = | G
60.000 | 2.000 | 30 m.p. | Cast iron pipes diameter 4 inch |
19.500 | 1.500 | 13 m.p. | Pipe diameter 3 inches (iron) |
24119/320
Page 29
To the Honorable Chairman of the Administrative Committee
Subject: Al-Sinak Building
I agree to reduce all prices listed in the contract submitted
by us by 3% only, three percent
Engineer
Saleh Yusuf
⟦illegible⟧
1937/5/8
Page 30
p. ( 23 )
Brought forward from the previous page
⟦line⟧
Dinar | Fils
24119 | 225
Deduct % from all prices (if the bidder so desires)
Add 5% as a reserve amount that may or may not be spent
by order of the Administrative Committee ( Contingoncies )
1205/966
Grand Total
25325/281
⟦Resident Engineer Abdul Sahib Yusuf⟧
⟦Only twenty-five thousand three hundred and twenty-five dinars⟧
⟦and two hundred and eighty-one fils only⟧
⟦illegible⟧